A cold and crisp day in the wood

Published by Jonathan on

Simon on the ridge

Tuesday saw a team of us out in the frost and sunshine trimming and shaping shingles. Simon was hanging the shingles and is now close to the ridge. We estimate about another 250 shingle to go to complete the south side.

Kit delivered us some more shingle rounds and we hope to spend next week preparing a load more ready for hanging.

The south side of the roof at the end of the day